Dundas Street Construction/Service Impacts

November 2025

November 28,2025

Previous Contractor: Moretti Contracting Ltd

Current Contractor: Sam Rabito
Project Limits: Dixie Road to Universal Drive
Overall Status: 96% complete
Expected Completion: End of December

 

Work Completed by previous contractor (Moretti) up to today:

  • All watermain mainline and service connections except for 1607 and 1470 Dundas St E
  • Completed commissioning at 1607 & 1470 Dundas Street East
  • All final road asphalt and line painting has been completed
  • Sod placement is at 90%

 

Upcoming Work for current contractor (Sam Rabito):

  • 1607 Dundas St E Connection: Scheduled to be complete by Friday, December 14th
    • Communications
      • Water Interruption to be delivered 5 days in advance of the work
      • Ambassador will visit all local businesses
    • Traffic and Entrances
      • Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      • Entrance will be opened back up by end of day
      • Entrance west of Mattawa will remain open
      • The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of entrance will be performed immediately after connection
      • Sod restoration will be done within 1-2 weeks
      • Weather permitting, driveway asphalt will be restored within 1 week depending on subcontractor availability

 

  • 1470 Dundas St E Connection: Scheduled to be complete by Friday, December 19th (night work required)
    • Communications
      • Water Interruption and Noise By-law Exemption Notices to be delivered 5 days in advance of the work
      • Ambassador will visit all local businesses
    • Traffic and Entrances
      • Work is located completely within the boulevard, no entrances are blocked
      • Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      • Pedestrians will be directed to cross on the north side with signage
      • The sidewalk will be reopened after the work is complete with restoration
      • Miway discussions will be revisited from previous shut down, the bus stop will be temporarily closed during active construction overnight
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of the sidewalk will be performed immediately after connection
      • Weather permitting, sod restoration will occur within 1 week of completion of the work

 

  • Miscellaneous Restoration and Clean Up: To be completed concurrently with the service connection work, all complete by the end of the calendar year
    • Restoration
      • Any remaining sod work that can be completed will be completed. Anything that cannot be completed due to weather will be addressed in the Spring
      • Temporary asphalt curbs and sidewalks will be touched up for winter
    • Traffic Loops
      • Several traffic loops will be reinstated
      • These will be isolated to 1-2 lanes being obstructed in signalized intersections for a short period while the loop is restored.
    • Removal and disposal of any leftover pipe, material, traffic controls, signage, etc.

 

Nov 7th, 2025 

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 96% complete
Expected Completion: Mid-November (weather permitting)

Work Completed:

  • Completed commissioning at 1607 & 1470 Dundas Street East
  • Driveway asphalt paving completed
  • Paving was completed from Dixie Road to Universal Drive on both the north and south side of the road
  • Sod placement is currently at 85%
  • Road asphalt work on Dundas
  • Line painting completed
  • Watermain connection at Dixie & Dundas

Watermain Connection at Dixie & Dundas:

  • Traffic and Entrances
      • Westbound curb lane has been reopened between Neilco Court and Dixie Road
      • Sidewalks at the northeast corner of the Dixie/Dundas intersection have been reopened
    • Restoration
      • Temporary road restoration has been completed, and traffic has been restored

The connections at 1470 & 1607 Dundas were not completed this week due to complications with the contractor. They could not complete the connections due to weather and safety concerns. All major items including restoration have been completed. We are meeting on Monday to discuss our options on the remaining two connections and localized restoration. We will send you both an update as soon as we have a clear path forward.

Nov 4th, 2025

18-1310C – Dundas WM Progress Update November 4th 

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 96% complete (see attached map)
Expected Completion: Mid-November (weather permitting)

Work Completed:

  • Completed commissioning at 1607 & 1470 Dundas Street East
  • Driveway asphalt paving completed
  • Paving was completed from Dixie Road to Universal Drive on both the north and south side of the road
  • Sod placement is currently at 85%
  • Road asphalt work on Dundas
  • Line painting completed

Upcoming Work:

  • Watermain Connection at Dixie & Dundas: Tuesday, November 4th (night work required)
    • Communication
      • Water Interruption and Noise By-law Exemption Notices delivered Friday, October 31st
      • Ambassador has visited all local businesses to inform them of the additional night needed
      • PVMS signs have been adjusted to inform the travelling public about the lane restrictions during this final connection
    • Traffic and Entrances
      • Westbound curb lane will be closed during the duration of this work between Neilco Court and Dixie Road
      • Traffic management plans have been reviewed and approved
      • Paid duty officers will be on site 24hrs a day for the full duration of the work to ensure safe and orderly vehicular movement
      • Sidewalks at the northeast corner of the Dixie/Dundas intersection will be closed to pedestrian access during the duration of this work
      • Pedestrians will be being directed to cross on the south side with signage
      • No bus stops are affected
    • Restoration
      • Temporary road restoration will be completed upon finishing the connection and traffic will be restored to normal once the work has been completed
      • The final top asphalt will be completed within the following 2-3 weeks depending on subcontractor availability
      • Any sod will be restored within 1-2 weeks of completion
  • 1470 Dundas St E Connection: Scheduled for Wednesday, November 5th (night work required)
    • Communications
      • Water Interruption and Noise By-law Exemption Notices delivered Friday, October 31st
      • Ambassador has visited all local businesses
      • There will be no interruption to their fire service
      • All hydrants will be active
    • Traffic and Entrances
      • Work is located completely within the boulevard, no entrances are blocked
      • Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      • Pedestrians will be directed to cross on the north side with signage
      • The sidewalk will be reopened after the work is complete with restoration
      • Miway discussions have commenced, the bus stop will be temporarily closed during active construction overnight
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of the sidewalk will be performed immediately after connection
      • Final sidewalk restoration will be completed in 1-2 weeks of completion of the work
      • Sod restoration will occur within 1-2 weeks of completion of the work
  • 1607 Dundas St E Connection: This work was postponed to Friday, November 7th
    • Communications
      • Ambassador visited the businesses Friday, October 31st to let them know the work would be rescheduled
      • Notice of access interruption are being delivered today
      • There will be no water interruptions for this connection
      • Ambassador will be talking to all the businesses today
    • Traffic and Entrances
      • Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      • Entrance will be opened back up by end of day
      • Entrance west of Mattawa will remain open
      • The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of entrance will be performed immediately after connection
      • Final restoration will be completed in 2-3 weeks
      • Sod restoration will be done within 1-2 weeks
      • Driveway asphalt will be restored within 2-3 weeks depending on subcontractor availability

————————————————————————————————————————————————————————————————————

October 2025

Oct 31, 2025 

18-1310C – Dundas WM Progress Update Oct 31st

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 96% complete (see attached map)
Expected Completion: Mid-November (weather permitting)

Work Completed:

  • Completed commissioning at 1607 & 1470 Dundas Street East
  • Driveway asphalt paving completed
  • Paving was completed from Dixie Road to Universal Drive on both the north and south side of the road
  • Sod placement is currently at 85%
  • Road asphalt work on Dundas
  • Line painting completed

Upcoming Work:

  • Watermain Connection at Dixie & Dundas: Additional night is needed next Tuesday, weather dependant (night work required)
    • Communication
      • Water Interruption and Noise By-law Exemption Notices delivered today
      • Ambassador has visited all local businesses to inform them of the additional night needed
      • PVMS signs have been adjusted to inform the travelling public about the lane restrictions during this final connection
    • Traffic and Entrances
      • Traffic has been reopened ahead of the weekend
      • Westbound curb lane will be closed during the duration of this work between Neilco Court and Dixie Road
      • Traffic management plans have been reviewed and approved
      • Paid duty officers will be on site 24hrs a day for the full duration of the work to ensure safe and orderly vehicular movement
      • Sidewalks have been reopened ahead of the weekend
      • Sidewalks at the northeast corner of the Dixie/Dundas intersection will be closed to pedestrian access during the duration of this work
      • Pedestrians will be being directed to cross on the south side with signage
      • No bus stops are affected
    • Restoration
      • Temporary road restoration will be completed upon finishing the connection and traffic will be restored to normal once the work has been completed
      • The final top asphalt will be completed within the following 2-3 weeks depending on subcontractor availability
      • Any sod will be restored within 1-2 weeks of completion
  • 1470 Dundas St E Connection: Scheduled for Wednesday, November 5th (night work required)
    • Communications
      • Water Interruption and Noise By-law Exemption Notices delivered today
      • Ambassador has visited all local businesses
    • Traffic and Entrances
      • Work is located completely within the boulevard, no entrances are blocked
      • Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      • Pedestrians will be directed to cross on the north side with signage
      • The sidewalk will be reopened after the work is complete with restoration
      • Miway discussions have commenced, the bus stop will be temporarily closed during active construction overnight
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of the sidewalk will be performed immediately after connection
      • Final sidewalk restoration will be completed in 1-2 weeks of completion of the work
      • Sod restoration will occur within 1-2 weeks of completion of the work
  • 1607 Dundas St E Connection: This work has been postponed and tentatively scheduled for next Friday, due to the weather
    • Communications
      • Ambassador visited the businesses in person today to advise them
    • Traffic and Entrances
      • Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      • Entrance will be opened back up by end of day
      • Entrance west of Mattawa will remain open
      • The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of entrance will be performed immediately after connection
      • Final restoration will be completed in 2-3 weeks
      • Sod restoration will be done within 1-2 weeks
      • Driveway asphalt will be restored within 2-3 weeks depending on subcontractor availability

 

October 29, 2025

18-1310C – Dundas WM Progress Update Oct 29th

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 96% complete (see attached map)
Expected Completion: Mid-November (weather permitting)

Work Completed:

  • Completed commissioning at 1607 & 1470 Dundas Street East
  • Driveway asphalt paving completed
  • Paving was completed from Dixie Road to Universal Drive on both the north and south side of the road
  • Sod placement is currently at 85%
  • Road asphalt work on Dundas
  • Line painting completed
  • All traffic barrels have been removed, except at the Dixie Road lane reduction for tonight’s connection work

Upcoming Work:

  • Watermain Connection at Dixie & Dundas: Monday–Thursday this week (two nights of work completed, two nights remaining) additional night may be needed, weather dependant
    • Communication
      • Water Interruption and Noise By-law Exemption Notices delivered Wednesday, October 22nd
      • Ambassador has visited all local businesses to inform them of the additional night needed (Thursday night)
      • Water Interruption and Noise By-Law Exemption Notices for Thursday night delivered Tuesday, October 28th
      • Additional night may be needed for connection
      • PVMS signs have been adjusted to inform the travelling public about the lane restrictions during this final connection
    • Traffic and Entrances
      • Westbound curb lane will continue to be closed during the duration of this work between Neilco Court and Dixie Road
      • Traffic management plans have been reviewed and approved
      • Paid duty officers are on site 24hrs a day for the full duration of the work to ensure safe and orderly vehicular movement
      • Sidewalks at the northeast corner of the Dixie/Dundas intersection are closed to pedestrian access during the three days of work
      • Pedestrians are being directed to cross on the south side with signage
      • No bus stops are affected
    • Restoration
      • Temporary road restoration will be completed upon finishing the connection and traffic will be restored to normal once the work has been completed
      • The final top asphalt will be completed within the following 2-3 weeks depending on subcontractor availability
      • Any sod will be restored within 1-2 weeks of completion
  • 1607 Dundas St E Connection: Expected to be completed by Friday, October 31st (daytime work only and weather dependant)
    • Communications
      • Water interruption notices were delivered Tuesday, October 29th
      • Ambassador has visited all local businesses
    • Traffic and Entrances
      • Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      • Entrance will be opened back up by end of day
      • Entrance west of Mattawa will remain open
      • The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of entrance will be performed immediately after connection
      • Final restoration will be completed in 2-3 weeks
      • Sod restoration will be done within 1-2 weeks
      • Driveway asphalt will be restored within 2-3 weeks depending on subcontractor availability
  • 1470 Dundas St E Connection: Scheduled for Wednesday, November 5th (night work required)
    • Communications
      • Water interruption notices to be delivered this week
      • Ambassador will be visiting all businesses impacted
    • Traffic and Entrances
      • Work is located completely within the boulevard, no entrances are blocked
      • Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      • Pedestrians will be directed to cross on the north side with signage
      • The sidewalk will be reopened after the work is complete with restoration
      • Miway discussions have commenced, the bus stop will be temporarily closed during active construction overnight
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of the sidewalk will be performed immediately after connection
      • Final sidewalk restoration will be completed in 1-2 weeks of completion of the work
      • Sod restoration will occur within 1-2 weeks of completion of the work

Oct 27, 2025

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 95% complete (see attached map)
Expected Completion: Mid-November (weather permitting)

Work Completed:

  • Completed commissioning at 1607 & 1470 Dundas Street East
  • Driveway asphalt paving completed
  • Paving was completed from Dixie Road to Universal Drive on both the north and south side of the road
  • Sod placement is currently at 85%
  • Road asphalt work on Dundas
  • Line painting completed
  • All traffic barrels have been removed, except at the Dixie Road lane reduction for tonight’s connection work

Upcoming Work:

  • Watermain Connection at Dixie & Dundas: Monday–Wednesday this week (three nights of work)
    • Communication
      • Water interruption and Noise By-law Exemption Notices delivered Wednesday, October 22nd
      • Ambassador has visited all local businesses
      • PVMS signs have been adjusted to inform the travelling public about the lane restrictions during this final connection
    • Traffic and Entrances
      • Westbound curb lane will continue to be closed during the duration of this work between Neilco Court and Dixie Road
      • Traffic management plans have been reviewed and approved
      • Paid duty officers will be on site 24hrs a day for the full duration of the work to ensure safe and orderly vehicular movement
      • Sidewalks at the northeast corner of the Dixie/Dundas intersection will be closed to pedestrian access during the three days of work
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
    • Restoration
      • Temporary road restoration will be completed upon finishing the connection and traffic will be restored to normal by Thursday of this week
      • The final top asphalt will be completed within the following 2-3 weeks depending on subcontractor availability
      • Any sod will be restored within 1-2 weeks of completion

 

  • 1607 Dundas St E Connection: Expected to be completed by Friday, October 31st (daytime work only)
    • Communications
      • Water interruption notices to be hand delivered tomorrow
      • Ambassador will be visiting all businesses impacted tomorrow
    • Traffic and Entrances
      • Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      • Entrance will be opened back up by end of day
      • Entrance west of Mattawa will remain open
      • The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      • Pedestrians will be directed to cross on the south side with signage
      • No bus stops are affected
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of entrance will be performed immediately after connection
      • Final restoration will be completed in 2-3 weeks
      • Sod restoration will be done within 1-2 weeks
      • Driveway asphalt will be restored within 2-3 weeks depending on subcontractor availability
  • 1470 Dundas St E Connection: Scheduled for Wednesday, November 5th (night work required)
    • Communications
      • Water interruption notices to be delivered this week
      • Ambassador will be visiting all businesses impacted
    • Traffic and Entrances
      • Work is located completely within the boulevard, no entrances are blocked
      • Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      • Pedestrians will be directed to cross on the north side with signage
      • The sidewalk will be reopened after the work is complete with restoration
      • Miway discussions have commenced, the bus stop will be temporarily closed during active construction overnight
      • Temporary westbound curb lane reduced during connection work
    • Restoration
      • Temporary restoration of the sidewalk will be performed immediately after connection
      • Final sidewalk restoration will be completed in 1-2 weeks of completion of the work
      • Sod restoration will occur within 1-2 weeks of completion of the work

 

Oct 24, 2025

Here’s a summary of the work completed recently and what’s coming up next for the Dundas Street East Project (18-1310C2):

Contractor: Moretti Contracting
Project Limits: Dixie Road to Universal Drive
Overall Status: 95% complete (see attached map)
Expected Completion: Mid-November (weather permitting)

18-1310C – Dundas WM Progress Update Oct 24th

Work Completed Last Week:

  1. Began laying sod (work still in progress)
  2. Completed commissioning at 1607 & 1470 Dundas Street East
  3. Driveway asphalt paving completed
  4. Began Dundas Street asphalt restoration, including nighttime line painting

Upcoming Work:

  1. Road Asphalt on Dundas:
    1. Communications
      1. PVMS signs are placed at key locations to inform travelling public
      2. Ambassadors are visiting local business
    2. Traffic and Entrances
      1. Westbound (north side)
        1. Asphalt works complete
        2. Line painting has been completed from Universal to Wharton, the remaining line painting will be complete by the end of the week
        3. All entrances and intersections will remain open with 4 signs reading “Businesses Open During Construction” along the length of the road to indicate that businesses are open
      2. Eastbound (south side)
  1. Expected completion by end of week
  2. During work over the next 2 days may have limited access or turning movement into entrances
  3. Left turn lanes at times will be not available due to paving through the intersections – paid duty officers will be on site to support safe traffic movement
  4. Line painting will be completed by the end of the week, dependant on weather
  5. Once paving work is complete, all entrances will be fully opened
  6. All entrances will be reopened for the weekend

 

  1. Sod Placement: Ongoing – expected completion by end of this week, excluding any work identified below

 

  1. Watermain Connection at Dixie & Dundas: Scheduled for Monday–Wednesday next week (three nights of work)
    1. Communication
      1. Water interruption and Noise By-law Exemption Notices delivered Wednesday, October 22nd
      2. Ambassador has visited all local businesses
      1. PVMS signs will be adjusted to inform the travelling public of the lane restrictions during this final connection
    1. Traffic and Entrances
      1. Lane restrictions will be in place for the duration of work
      2. Traffic management plans have been reviewed and approved
      3. Paid duty officers will be on site 24hrs a day for the full duration of the work to ensure safe and orderly vehicular movement
      4. Sidewalks at the northeast corner of the Dixie/Dundas intersection will be closed to pedestrian access during the three days of work
      5. Pedestrians will be directed to cross on the south side with signage
      6. No bus stops are affected
    2. Restoration
      1. Temporary road restoration will be completed upon finishing the connection and traffic will be restored to normal by Thursday of next week
      2. The final top asphalt will be completed within the following 2-3 weeks depending on subcontractor availability
      3. Any sod will be restored within 1-2 weeks of completion

 

  1. 1607 Dundas St E Connection: Expected to be completed by Friday, October 31st (daytime work only)
    1. Communications
      1. Water interruption notices to be issued by end of this week
      2. Ambassador will be visiting all businesses impacted
    2. Traffic and Entrances
      1. Work is located within the Mattawa entrance, and this entrance will be blocked while the connection is being made
      2. Entrance will be opened back up by end of day
      3. Entrance west of Mattawa will remain open
      4. The pedestrian access to sidewalks will be blocked on the north sidewalk adjacent to these works
      5. Pedestrians will be directed to cross on the south side with signage
      6. No bus stops are affected
      7. Temporary westbound curb lane reduced during connection work
    3. Restoration
      1. Temporary restoration of entrance will be performed immediately after connection
      2. Final restoration will be completed in 2-3 weeks
      3. Sod restoration will be done within 1-2 weeks
      4. Driveway asphalt will be restored within 2-3 weeks depending on subcontractor availability

 

  1. 1470 Dundas St E Connection: Scheduled for Wednesday, November 5th (night work required)
    1. Communications
      1. Water interruption notices to be delivered by Wednesday next week
      2. Ambassador will be visiting all businesses impacted
    2. Traffic and Entrances
      1. Work is located completely within the boulevard, no entrances are blocked
      2. Sidewalk on south side of the road, adjacent to the works, will be closed to pedestrian access
      3. Pedestrians will be directed to cross on the south side with signage
      4. The sidewalk will be reopened after the work is complete with restoration
      5. Miway discussions have commenced, the bus stop will be temporarily closed during active construction overnight
      6. Temporary westbound curb lane reduced during connection work
    3. Restoration
      1. Temporary restoration of the sidewalk will be performed immediately after connection
      2. Final sidewalk restoration will be completed in 1-2 weeks of completion of the work
      3. Sod restoration will occur within 1-2 weeks of completion of the work

For the watermain construction project 18-1310 C2, businesses will experience interruptions to their water supply on Tuesday October 28 at 10 pm until Wednesday October 29, 2025 at 8 am.

18-1310 C2 Water Interruption Notice – Dixie Road and Dundas Street East – Oct 28 25 – letter

Approximately 67 commercial units, which includes stores, offices, medical clinics, fast food restaurants and gas stations will be affected, at:

  • 3105 and 3130 Dixie Road
  • 1334, 1369, 1370, 1403, 1404 and 1425 Dundas Street East

Please find further details within the attached notice.

Other information about this construction project is available online at Project 18-1310 C – peelregion.ca.

Please send any questions to construction@peelregion.ca. This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

 

18-1310 C2 Night Work Notice – Dixie Road and Dundas Street East – Oct 27 25

For the watermain construction project 18-1310 C2, some upcoming work will be completed outside normal business hours. This work will take on the nights of Monday October 27 to Tuesday October 28, Tuesday October 28 to Wednesday October 29 and Wednesday October 29 to Thursday October 30, 2025, between 10:00 pm and 8:00 am at the intersection of Dixie Road and Dundas Street East.

More details are available in the attached notice for affected businesses, which will be posted online at https://peelregion.ca/construction/project-18-1310-c within the next few days.

Please send any questions to construction@peelregion.ca. This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

Update September/October 2025

18-1310C – Dundas WM Progress Update Oct 3_img

We have completed all connections to existing watermain system, as well as small and large diameter service connections except for the following:

  • Large diameter service (fire) at 1607 Dundas St E
  • Watermain connections to existing system at Dixie/Dundas intersection and at 1470 Dundas St E

Next week we aim to complete:

  • Large diameter service (fire) at 1607 Dundas St E and watermain connection to existing system at 1470 Dundas St E
  • Road asphalt on Dundas St E
  • Preparation for sod restoration

Following the replacement of the watermain for construction project 18-1310 C, we will be repairing affected driveways, roads, curbs, sidewalks, and sod (grass). This restoration work will take place along Dundas Street East between Dixie Road and Summerville Court / Universal Drive. It is expected to begin in October 1st, 2025 and to be completed by the end of October 2025.

More details are available in the attached notice for affected residents and businesses, which will be posted online at https://peelregion.ca/construction/project-18-1310-c within the next few days.

Please send any questions to construction@peelregion.ca . This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

18-1310 C2 – Restoration notice Sep 25 25

NOTICE: Sept 25, 2025

RC-2025-10-10

——————————————————————————————————————————————————–

August 2025

Over the past week we have:

  • Completed fire (large diameter) and domestic (small diameter) services at 1739 and 1825 Dundas St E
  • Completed large diameter service (fire) at 1995 Dundas St E
  • Completed watermain connection to the existing system at Nawbrook and Treadwells

Over this week we aim to complete:

  • The watermain connections to the existing system at Neilco (north side) and Wharton
  • The watermain interconnect between Jarrow and Neilco
  • The small diameter connections at 1505 and 1575 Dundas St E

 

————————————————————————————————————————–

Update July 29, 2025

Dundas St E WM Councillor July 15 Presentation

Please find attached our progress update image for your records.

Over the past week we have:

Completed watermain connection to existing system at Coram

  • Completed service connections 1820 Dundas St, 1770 (fire and domestic) 1945 (fire and domestic)
  • Completed 1 service at 1725, but still need to complete one more at other entrance

 

Over the next week we aim to complete:

 

  • Two watermain connections to existing system at Universal Dr. (east and north)
    • Both performed at night to minimize impacts
  • One watermain connection to existing system at Wharton Way (north side)
  • Large diameter service connection at 1938 Dundas St E

 

Update June 13, 2025

For the watermain construction project 18-1310 C2, businesses will experience brief interruptions (approximately 15 minutes) to their water supply on Tuesday June 17, 2025 between 6 am and 8 am.

Approximately 22 commercial units will be affected, at:

 

  • 3035 to 3101 Jarrow Avenue
  • 1490 to 1606 Sedlescomb Drive
  • 1565 Dundas Street East

Other information about this construction project is available online at Project 18-1310 C – peelregion.ca

Please send any questions to construction@peelregion.ca. This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

Update: May 14, 2025 

Please be advised that stop #0878 on WB Dundas Street at Neilco Court will be out of service effective 8:00am Thursday May 15 until further notice for continuing watermain construction works.

Patrons will be directed to the previous stop #1192 at Jarrow Avenue which is approximately 175 metres east.

Stop #0878 is serviced by Route 1W and 1CW with continued accessible bus service at Stop #1192.

For the watermain construction project 18-1310 C2, businesses will experience interruptions to their water supply on Thursday May 15, 2025 at 11 pm until Friday May 16, 2025 at 8 am.

Approximately 6 commercial units will be affected, at:

  • 1455, 1465, 1475 and 1490 Dundas Street East

Please find further details within the attached notice.

Other information about this construction project is available online at Project 18-1310 C – peelregion.ca

18-1310 C2 Water Interruption Notice – Dundas Street East – May 15 25 – letter for businesses

Please send any questions to construction@peelregion.ca. This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

For the watermain construction project 18-1310 C2, some upcoming work will be completed outside normal business hours. This work will take place from 11:00 pm on Thursday May 15, 2025 until 8:00 am on Friday May 16, 2025, Dundas Street East.

More details are available in the attached notice for affected businesses, which will be posted online at Project 18-1310 C – peelregion.ca within the next few days.

18-1310 C2 – Noise bylaw exemption Dundas St E May 15 16 25

Please send any questions to construction@peelregion.ca. This will allow our customer service team to direct the inquiry to the relevant staff and log it to inform future service enhancements.

UPDATE: April 2nd, 2025

WTR-0274 Dundas Street construction update V6 FINAL

UPDATE: April 2nd, 2025

Dundas Street Construction Update 🚜

I’ve been meeting regularly with Region of Peel staff to discuss the Dundas Street Watermain Replacement Construction and address concerns from residents and local businesses.

Please see below the link to the Power Point presentation with updates and successes from the immediate actions for the Regional Work on Dundas St East.

Dundas St E (Dixie to East Limit) WM Ward 1,3 Update – 2025 03 28

——————————————————————————————————————————————————

UPDATE: January 2025
Current Schedule and Status
– The project was originally planned to be completed by the end of 2024 but due to unknown buried foundations/structures within the roadway (at the depth of our watermain), progress has been slowed significantly and as a result an increased level of traffic management was needed to overcome these obstructions and keep moving forward,
– Because of these delays we missed our ability to perform some of the restoration in the suitable weather in the fall, so all permanent restoration will now by in the late Spring to early summer 2025.
– We will be commissioning the watermain in the very near future and once passed, the final connections and services can commence.
– Due to the tasks remaining, the crew has been working inside few of the chambers and compound areas where the travelling public would not see the crew down below ground. While in may appear that work isn’t being conducted at the surface that isn’t the case. During the commissioning of the watermain, there are mandated periods where no work can occur on the watermain itself until we can demonstrate that the pressure test and disinfection samples have all passed.
– The revised completion date is, as noted above, Late spring/early summer 2025.

Actions Moving Forward
– Similar to the Hanlan work at Burnhamthorpe and Applewood Trail, we will be providing you regular informal updates on the Dundas progress
– We are close to the commissioning stage and are currently preparing a draft notice, which will be circulated to your office, to the business impacted along Dundas outlining the next stage of the project and what to expect with transferring their service to the new watermain. The remaining construction and restoration is to be completed within the late spring timeline.
– We will be performing regular assessments of the traffic control measures to ensure what is in place is necessary.
– We continue to ensure the site is constantly maintained in a tidy and condense footprint and have followed up with onsite staff to remind them of the need for a organized, tidy site with clear traffic management setups. We do apologize with the about any perception of a messy site and will strive to keep a tidier site.

We have spoken with City staff and their work along Dundas is currently west of Ward 3. As the Dundas BRT project advances updates will be provided.

——————————————————————————————————-
Please be advised that stop #0878 on WB Dundas Street at Neilco Court will be out of service effective immediately until Friday February 21 for watermain construction works. 🚌
Patrons will be directed to the previous stop #1192 at Jarrow Avenue which is approximately 175 metres east.
Stop #0878 is serviced by Route 1W and 1CW with continued accessible bus service at Stop #1192.